Results

Scientific publications, technical reports, performance indicators and communications.

Theoretical Framework

The FdR-BIM performance measurement, impact assessment and benchmarking project adopts a comprehensive, systemic and systematic approach integrating the Triple Bottom Line framework (economic, environmental, social) and ESG criteria (Environmental, Social, Governance).

Performance measurement theoretical framework

Theoretical framework for performance measurement, impact assessment and benchmarking (Adapted from Rankin et al., 2008)

The framework considers:

  • Project inputs — Initial project resources and data
  • Project delivery system — Orchestrated structures, processes, actors and artifacts
  • Project constraints (time, cost, etc.) and organizational constraints (resources, etc.)
  • Mechanisms — Competencies/capacity/maturity, use of digital tools, degree of collaboration, other innovations
  • Outcomes — Environmental, social, economic and other results
  • Impact — Long-term effects measured through the impact value chain

Priority Performance Indicators

The following 17 priority measures have been identified and validated by public owner organizations (POOs) for deployment across all FdR-BIM pilot projects.

IndicatorMeasureDescription
CostCost predictabilityVariance between actual cost and initial estimate (%)
CostCost per unitAverage cost per installed unit ($/m², $/km, etc.)
TimeDuration predictabilityVariance between actual duration and initial estimate (%)
TimeTime per unitAverage installation time per unit
ProductivityLabor productivityProductivity measured in $/unit completed
QualityStakeholder satisfactionLevel of satisfaction with final product
SafetyLost time incidentsTime lost due to incidents / 100,000 hours
ScopeChange orders (cost) — clientClient-initiated changes (% of cost)
ScopeChange orders (cost) — contractorContractor-initiated changes (% of cost)
ScopeChange orders — clientTotal number of change orders (client)
ScopeChange orders — contractorTotal number of change orders (contractor)
ScopeRequests for information (RFI)Number of formal information requests
RiskRisk exposureTotal amount and score of identified risks
RiskRisk mitigation costTotal budgeted mitigation cost
SustainabilityWaste productionVolume of waste generated vs targets
SustainabilityCarbon footprintGHG emissions (CO₂ equivalent)
SustainabilityEnergy consumptionEnergy used (kWh) vs estimates

Complete Set of Identified Indicators

The following 43 measures were identified through literature review and interviews with POOs. They cover 9 key performance indicator categories.

1. Cost

IDMeasureDescription
1.1Cost predictabilityDifference between actual cost and estimate at a key milestone, expressed as percentage
1.2Cost per unit (estimated and actual)Average cost of an installed product or system ($/km, $/m²)
1.3Operating costAnnual operation and maintenance cost after completion, as % of construction cost

2. Time

IDMeasureDescription
2.1Duration predictabilityDifference between actual duration and initial estimate, expressed as percentage
2.2Time per unit (estimated and actual)Average installation time for a product or system (hours/m, days/m²)

3. Productivity

IDMeasureDescription
3.1Labor productivity — $/unitProductivity measured in dollars per completed unit
3.2Labor productivity — unit/hourProductivity measured in units per hour
3.3Decision latencyAverage time between decision initiation and final decision

4. Quality

IDMeasureDescription
4.1Stakeholder satisfactionLevel of satisfaction with final product after defect resolution
4.2Quality issues (punch list)Total number of non-conformities identified at substantial completion
4.3Defect cost — warrantyCost of rectifying defects during warranty period (% of construction cost)
4.4Defect resolution time — warrantyTime taken to rectify all defects during warranty period
4.5Rework rateProportion of work requiring rework after substantial completion

5. Safety

IDMeasureDescription
5.1Reportable incidentsNumber of reported incidents / 100,000 hours worked
5.2Lost time incidentsTime lost due to incidents / 100,000 hours worked

6. Scope

IDMeasureDescription
6.1Change order (Cost) — clientClient-attributable changes, as % of estimated construction cost
6.2Change order (Cost) — contractorContractor-attributable changes, as % of estimated construction cost
6.3Change order (Time) — clientClient-attributable duration changes, as % of estimated duration
6.4Change order (Time) — contractorContractor-attributable duration changes, as % of estimated duration
6.5Change orders — clientTotal number of client-initiated change orders
6.6Change orders — contractorTotal number of contractor-initiated change orders
6.7Number of claimsTotal number of claims submitted/recorded
6.8Total claim amountRatio of total awarded claim costs
6.9Requests for information (RFI)Number of formal information requests issued

7. Risk

IDMeasureDescription
7.1Number of quantified risksTotal number of risks identified for a project
7.2Risk exposureRisk profile characterized by total amount and score (severity × probability)
7.3Risk mitigation costTotal budgeted risk mitigation cost
7.4Risk materializationTotal cost of risks that materialized

8. Sustainability

IDMeasureDescription
8.1CertificationSustainability level assessed against standard practice checklist
8.2Material consumptionTotal quantity of materials used vs design estimates
8.3Waste productionVolume of waste generated vs project or industry targets
8.4Carbon footprintTotal GHG emissions (CO₂ equivalent) over lifecycle
8.5Waste recycling rateProportion of waste recycled or reused (%)
8.6Energy consumptionEnergy used (kWh) compared to baseline estimates
8.7Air pollutionLevel of air pollutants (particulates, NOₓ, SOₓ) vs standards
8.8Community impactSocial and environmental impact assessed through stakeholder feedback
8.9Water pollutionContaminants introduced to water bodies vs regulatory limits

9. Innovation

IDMeasureDescription
9.1Procurement typeNon-standard procurement practices compared to standard practices
9.2Management innovationNon-standard management practices compared to standard practices
9.3Lean implementation indexAdoption of Lean principles (waste reduction, continuous improvement)
9.4BIM adoption levelDegree of BIM integration measured by uses and actors involved
9.5Collaboration indexCollaboration measured through survey of project actors
9.6Technological innovationNew technologies deployed in project processes

Project Publications

2025

Authors: Lerognon, V., Poirier, E., Hochscheid, E., & Hallin, G.

Publication: Proceedings of Smart and Sustainable Built Environment Conference Series, 186–195

Access publication →

Authors: Omar Maher & Erik Poirier

Publication: Joint CSCE Construction Specialty - CRC 2025

Authors: Seyed Mohammad Ehsan Tabatabaee, Luciana Gondim de Almeida Guimarães, Ivanka Iordanova, & Erik Poirier

Publication: Joint CSCE Construction Specialty - CRC 2025

Authors: Tabatabaee, S. M. E., Iordanova, I., & Poirier, E.

Publication: Proceedings of the Canadian Society for Civil Engineering Annual Conference 2024, Volume 3 (pp. 131–142). Springer Nature Switzerland.

Access publication →

Authors: Victoria Lerognon, Erik A. Poirier, Elodie Hochscheid, & Gilles Halin

Publication: Joint CSCE Construction Specialty - CRC 2025


Technical Reports

2026

Auteurs: Project team

Publication: Government BIM Roadmap — Activity 1.3.1: Identify Performance Indicators

Download report (PDF) →

2025

Authors: Victoria Lerognon & Erik Poirier

Publication: Government BIM Roadmap — Activity 3.1.3: Examine the current policy and regulatory framework and understand its effect on BIM implementation

Download report (PDF) →


Communications and Presentations

Coming soon